Timebox attributes
Contents: |
|---|
About timebox attributes
The box details dialog in the Board module provides the following information about the timebox (such as Sprint, Iteration, and PI):
box ID
box name
box start and end dates
task period alignment
Access box details
To prompt box details dialog:
Click triple dots (More actions) on the selected timebox.
Select Edit from the dropdown menu.
Manage box details
All data displayed on the task details dialog are editable, allowing you to manage your timebox details on the fly.
Box ID
Click the icon next to the ID to copy it. You will need the box ID to synchronize tasks in the scope of your box.
Box name
The default name for the Iteration box type is “Iteration.” Inline edit the box name to better reflect your organization's terminology.
Box start and end dates
The start and end dates of the timebox depend on the task period alignment. However, you can manually change one or both dates should your current iteration require it.
Task period alignment
You can also change the task period alignment directly in the box details dialog. For more information, see the Task period alignment page.
Box status
The dropdown menu under the More actions (…) lets you change the status of the box. Alternatively, right-click the timebox heading to prompt the box status menu.
The status-related properties are described in the table below:
Box status | Description |
|---|---|
Not started (gray) | When you set the timebox status to "Not started," you can:
|
In Progress (blue) | When you set the Timebox status to "In Progress," you can:
|
Closed (green) | When you set the Timebox status to "Closed":
|