Dependencies (Infobar)
Overview
The Dependencies section displays a list of task dependencies present in a given box and groups them:
Correct dependencies (dependencies exist and affect scheduling properly)
Broken dependencies (dependencies exist but they do not affect scheduling as they should, if at all)
Non-scheduling dependencies (soft dependencies—dependencies that show task relationships but do not affect scheduling)
The dependencies the Infobar sums up dependencies in each category and displays the total on each group. That applies to dependencies that:
Connect two tasks that both are in the scope of the current box.
Connect one task that is in the scope of the current box and the other one that is in the scope of another box (for example, a cross-project dependency). Such a dependency is indicated with a crossed-eye icon.
Dependency details
Expand a dependency to see the following information:
Source task
Target task
Task key
Task dates
Status
Dependency type
Dependency details
Lag time (if applicable)
ASAP (if applicable)
Actions in the dependencies tab
Search for tasks
The search bar lets you find a specific task (or tasks) whose dependencies you want to inspect.
You can narrow down the search results to show only those dependencies of the selected tasks that have the ASAP mode enabled or disabled.
Focus on source/target task
Click More actions (…) to open the context menu.
From the dropdown, select Focus on source or Focus on target.
The “Focus on” feature focuses the Gantt timeline on the source or target task of a selected dependency. The app adjusts the timeline and highlights the source or target task.
Only the tasks that belong to the scope of the current box can be focused.
The video presents the Focus on task feature.
Edit dependency
Click More actions (…) to open the context menu.
From the dropdown, select Edit.
The video presents how to edit a dependency.
Delete dependency
Click More actions (…) to open the context menu.
From the dropdown, select Delete.
Click Delete to confirm the action.
Out-of-view dependencies
Out-of-view dependencies cannot be displayed on the Gant chart but are included on the dependency list. The crossed-eye icon indicates the out-of-view tasks when one of the dependent tasks (source or target) is:
in the scope of the current box
not visible due to the active filters or search query
If the task is out of scope or filtered out, you cannot snipe to it, either.