Milestones
Introduction
You can track project milestones using the Infobar section in the Gantt module. Navigate to the selected milestone by clicking on the "Target" icon next to the milestone on the list.
Convert tasks to milestones
Milestones can be interpreted as:
Markers of reaching an identifiable stage in any task or project.
Software release life cycle states.
On the timeline, milestones are represented as diamonds.
Milestones represent a point in time - milestone duration is 0 days.
Parent tasks cannot be converter to milestones.
If a task has children in the task tree (WBS) it can't be converted into a milestone - scheduling mode interactions between parent/child would not be possible.
Convert a single task to a milestone
To convert a single task to a milestone or vice versa, right-click on the selected task (on the task list) or use the ". . ." button in the vertical dialog.
You can also use inline editing to turn a task into a milestone.
Start/end date recalculation
During conversion, the task end date is set as the milestone date.
Before conversion:
After conversion:
Convert multiple to milestones / tasks
Use the multi-select option to select a few tasks and milestones and right-click to "Convert all to...":
Milestone
Task
When you select a milestone and a task and right-click "Convert all to.. > Task":
A milestone is converted to a task.
A task remains unchanged because it is already a task.
Convert a task with one date to a milestone
When a task with one date (“Start Date” or “End Date”) is converted to a milestone, the “Start Date” becomes the same as the “End Date”.
Create a basic task as a milestone
Click the + (plus icon) > Create task > Basic task.
Fill in the task information.
Activate the toggle switch.
Milestone synchronization
You can synchronize milestone information using the "Label" field. When you convert a task to a milestone, the app will create a #milestone label:
Labels will be added or removed in the following scenarios:
A task is converted into a milestone -> the #milestone label in Jira is added.
A milestone is converted into a regular task -> the #milestone label in Jira is removed.
A milestone is converted into a parent task -> the #milestone label in Jira is removed.
Note: Depends on field mapping.
Milestone overview - Infobar
You can show the list of milestones using the Gantt's Infobar:
Only milestones expanded on the Gantt chart are visible on the list.
If a user wants to see only milestones from selected parent tasks, they need to expand those parent tasks and collapse parent tasks they are not interested in.
If a user wants to see all the milestones in the program, they need to expand all of the tasks by clicking "Expand all" on a tree root column header.
Dependencies vs milestones
See the Dependencies vs milestones page for more information.
Need support? Create a request with our support team.
Copyright © 2005 - 2025 Appfire | All rights reserved.
