Manual KR
This page is about OKR for Jira Cloud. Using Data Center? Click here.
In the manual mode, the user updates the progress of the key result.
There are two main components of the manual KR progress:
KR values (start, current, target)
Measure as (value unit)
Note the “KR” icon for the manual KR:
Available KR values and units
The progress of the manual KRs must be updated manually. For that reason, you need to first define their values and unit.
KR values
There are two KR values related to the KR progress that reflect what you want to achieve with a specific OKR:
Start - The initial state of the KR’s progress. When creating a KR, you define the starting value once, but you can edit it if needed.
Current - The value indicating progress. As your teams work toward completing the KR, you will manually update this value.
Target - The goal you want to achieve with a KR. When creating a KR, you define the target value once, but you can edit it if needed. As your teams work toward completing the KR, the current value should be getting closer to the target value for successful completion.
KR value units (Measure as)
The value units should match the KR goal you want to achieve. Since there can be many different numeric goals, the OKR module gives you the flexibility to choose one of the many different units:
Standard - Numeric (no unit) and percent (%).
Currency - USD ($), EUR (€), GBP (£), BRL (R$), INR (₹), CHF (CHf), IDR (Rp), ZAR (R).
How to set the KR value and unit
On the KR creation screen, you can set the start and target values and units.
On the KR creation screen, select Update manually under Progress.
Below the Progress, define the:
Measure as unit (for example, “Percent”)
Current value (This is the same as the “start” value)
Target value (the goal of the KR)
How to change the start and target values and unit
The start and target values can be changed anytime on the OKR details page.
In the Progress section, click the pen icon.
On the Change start and desired value of the key result screen, update the start value and the target (desired) value.
If you want the new values and a unit to be applicable to the previous KR updates, check the option below the start value.
How to update manual KR progress
You can update the current KR progress value on the KR update screen. (The field is grayed out for the auto-KRs.)
As the current value increases, so does the app calculate the progress according to the formula:
(current - start) / (target - start) = progress x 100%
KR target on track: Example
Say you want to conduct a series of UX interviews to gather feedback from current customers about the app you launched a few months ago. Your KR could be: “Conduct 25 customer interviews to understand product usage and satisfaction.”
Since you have not started any interviews yet, the values for such KR would be as follows:
Start value: 0
Target value: 25 (you want to conduct 25 interviews in a specific OKR period)
Current value: 4 (4 interviews conducted so far)
The unit for such KR would be just numeric because you are after a specific amount of interviews. Once a few interviews are conducted, you can update the current value to reflect the progress, for example, 4.
As a result:
(4 - 0) / (25 - 0) = 0.16 x 100% = 16%
KR target surpassed: Example
What if your teams went that extra mile and conducted 3 more interviews than initially planned (25)? In such a case, the progress will exceed 100%.
Start value: 0
Target value: 25 (you want to conduct 25 interviews in a specific OKR period)
Current value: 28 (28 interviews conducted in total)
(28 - 0) / (25 - 0) = 1.12 x 100% = 112%
KR below target: Example
You want to reduce customer churn from 10% to 5%. Unfortunately, due to some unforeseen events, the churn went up to 13%.
Start value: 10
Target value: 5 (you want to conduct 25 interviews in total in a specific OKR period)
Current value: 13 (churn has increased to 13%)
As a result:
(13 - 10) / (5 - 10) = -0.6 x 100% = -60%
How convert to manual KR
Converting from an auto-KR to a manual KR means your KR's progress will no longer update automatically based on the linked issues.
Upon the conversion, the issues will remain connected, but they will no longer affect the progress. Your current progress will remain unchanged, and no previous updates will be deleted.
Track manual KR progress
You can track auto-KR progress (and status) changes on the OKR details side panel and the OKR details page (the Status changes and Activity sections).
The details panel and the details page list your own status changes. The OKRobot bot will not post any updates for the manual KR, but you will see automatic comments on the updates, such as when you create KR and update its values.
Progress updates on the OKR details side panel | Progress updates on the OKR details page (Status changes) |
|---|---|
Need support? Create a request with our support team.
Copyright © 2005 - 2025 Appfire | All rights reserved.